SAMPLE & VERSION CONTROL

What to record before approving an OEM sample

A sample should not become the production reference through an email that only says approved. The approval record must identify what was tested, under which conditions and which version can proceed.

5-minute control guide · Published September 2, 2026

1. Identify the sample

  • Project and sample reference
  • Supplier and manufacturing route within the agreed disclosure scope
  • Product description, dimensions, material and revision
  • Packaging or label version when included in the approval
  • Date received and condition on arrival

2. Record how it was evaluated

  • Application, equipment and workpiece
  • Test quantity and operating conditions
  • Acceptance criteria and comparison reference
  • Who performed the test and who reviewed the result
  • Photographs, measurements or observations connected to the sample code

3. Separate findings from the decision

  • Accepted findings
  • Supplier-stated information that was not independently tested
  • Open deviations and required corrective action
  • Revised sample requirement
  • Approved, conditionally approved or rejected decision

4. Transfer approval into the order record

Production should refer to the approved sample and its written specification. If the supplier proposes a change, the buyer can then compare it against a known baseline instead of relying on memory.

  • Approved sample reference on the purchase and production record
  • Final specification and packaging revision
  • Inspection points derived from the acceptance criteria
  • Change-control owner and reapproval trigger